Ada County Highway District

38th Street, Bush Avenue to Sunset Avenue

Construction Update as of October 1, 2021: Demo complete. Grade work complete. East and west side curbing complete.  DIs have been placed. Sidewalk work ongoing. Nearly complete. Main line paving complete. Concrete driveway work ongoing. Miscellaneous landscape repair work ongoing.

Construction Update as of September 23, 2021: Demo complete. Grade work complete. East and west side curbing complete. DIs have been placed. Sidewalk work ongoing - nearly complete. Main line paving half complete.

Construction Update as of September 17, 2021: Demo complete. Grade work ongoing. East and west side curbing nearly complete. Minor radius work remaining. 2 out of the 3 DIs have been placed. Sidewalk work ongoing. Paving is scheduled for September 21st. 

Construction Update as of September 10, 2021: Demo complete. Grade work ongoing. East and west side curbing nearly complete. Minor radius work remaining. Sidewalks are expected to be complete next week. Paving is scheduled for September 14th. 

Construction Update as of September 3, 2021: Miscellaneous demo continues. Grading work ongoing. East side curbing nearly complete. West side to start early next week. Utility work ongoing. Formwork for sidewalks has been partially set. 

Construction Update as of August 26, 2021: Miscellaneous demo continues. Grading work ongoing. Curbing is expected to start next week. Utility work ongoing. Light poles have been set and relocated to clear sidewalk. 

Construction Update as of August 19, 2021: Miscellaneous demo work continues. Grading work is ongoing. Curbing is expected to start next week. Utility work is ongoing. Light poles have been set and relocated to clear sidewalk. 

Construction Update as of August 13, 2021: Contractor has mobilized to the site. Miscellaneous demo work has started. Contractor has trimmed trees. Survey stakes have been set for construction limits, etc. Milling complete

Construction Update as of August 6, 2021: The contractor has mobilized to the site. Miscellaneous demo work has started. Survey stakes have been set for construction limits. 

Construction Update as of July 30, 2021: ACHD is coordinating street light replacement and relocation with the City of Boise and Idaho Power. The contractor anticipates starting work on August 2nd. 

Construction Update as of July 6, 2021: ACHD is coordinating street light replacement and relocation with the City of Boise and Idaho Power.  

Construction Update as of June 11, 2021: The Preconstruction Meeting was held on May 21st. ACHD is currently waiting on project submittals from the contractor before a Notice to Proceed is issued. 

Construction Update as of April 29, 2021: The Ada County Highway District will start construction on the 38th Street project between Bush Avenue and Sunset Avenue as early as mid-May. Construction is anticipated to be complete in the fall. 

Construction impacts

  • Lane restrictions
  • Temporary on-street parking impacts
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7a.m. to 7 p.m. unless otherwise approved 
  • The contractor will work with homeowners to maintain access

Project description

  • Remove the barrier just south of Bush Avenue
  • Add curb, gutter and sidewalk on the west side of the street
  • Construct curb and gutter on the east side of the street
  • Add pedestrian ramps
  • Rebuild street to meet modern standards
  • Majority of improvements will be completed within the public right-of-way
  • View the design*

 

Project purpose

  • Increase connectivity in the neighborhood
  • Provide pedestrian facilities for children walking to school

 

Project considerations

  • Safety
  • School children and pedestrians
  • Drainage
  • Bicyclists
  • Private property impacts
  • Connectivity

 

 

Return to Projects

Related Documents

Project Manager


We Drive Quality Transportation For All Ada County ~
Anytime...Anywhere

Ada County Highway District © 2017
For Questions or problems with this Web site contact the Webmaster