2020 Federal Aid Capital Maintenance

Construction Update as of November 20, 2020:  A preconstruction conference was held on June 18th. The Notice to Proceed was July 6th. 

General Description:

This summer the Ada County Highway District will begin work on phase one of the 2020 Federal Aid Capital Maintenance project. This project includes pavement rehabilitation, select pipe replacement and pedestrian ramp upgrades. Work will be done on the following segments of road:

  • 13th Street, Alturas Street to Brumback Street--Concrete work is complete. Roadway work will be done in Spring 2021.
  • Cole Road, New York Canal to Latigo Drive: Complete
  • Hill Road Parkway, Horseshoe Bend Road to Seaman Gulch Road - Complete
  • Horseshoe Bend Road, State Street to Cemetery Entrance - Concrete work is nearly complete. Roadwork will be done spring 2021.
  • Locust Grove Road, Ustick Road to McMillan Road--Concrete work is complete. Roadway work will be done spring 2021.
  • Pine Avenue, Linder Road to Meridian Road - Complete
  • Technology Way, Columbia Road to State Highway 21 - Complete

Time Frame

Start Date:
July 2020
End Date:
November 2020

Return to Projects

Related Documents

Project Manager


We Drive Quality Transportation For All Ada County ~
Anytime...Anywhere

Ada County Highway District © 2017
For Questions or problems with this Web site contact the Webmaster