Construction Updates as of (5/17/19):

Crews are working on installing seepage beds, storm drains, and intersection bases. There is ongoing utility work. Idaho Power is currently pulling their old poles.

Sidewalks on the east side of the road between Chinden and DeMeyer began the week of May 13th and will continue heading north. Work between Ustick and McMillan will follow the work between McMillan and Chinden.

Traffic shifted to the west mid-February to allow for work on the east side of Cloverdale Road. Crews are also working on seepage bed and storm drain installation. There are ongoing utility relocations. 

Construction started on January 7th, 2019

This project is being built in conjunction with the Cloverdale, Ustick to McMillan project.

The contractor for this project is Central Paving.

General Description:

  • Widen Cloverdale Road between McMillan Road and Chinden Boulevard to two lanes in each direction, with a center turn lane.
  • Add buffered bike lanes.
  • Construct curb, gutter and sidewalk.

Materials from the October 24th Open House

 

Return to Projects

Related Documents

Project Manager

Brian McCarthy
projects@achdidaho.org


We Drive Quality Transportation For All Ada County ~
Anytime...Anywhere

Ada County Highway District © 2017
For Questions or problems with this Web site contact the Webmaster