2021 Federal Aid Capital Maintenance Phase 2

Construction Update: May 27, 2022 - 

  • Edna Street, Five Mile Road to Patton Street:
    • Complete
  • Warm Springs Avenue, Starcrest Drive to Starview Drive:
    • Paving is complete. Manholes have been adjusted. Steel plates will be removed on May 20th. Striping is scheduled for May 20th.
  • Warm Springs Avenue, Glacier Drive to SH-21:
    • Paving is complete. Minor work will continue through early June, including manhole adjustments and permanent striping. 

Construction Update: May 20, 2022 - 

  • Edna Street, Five Mile Road to Patton Street:
    • Complete
  • Warm Springs Avenue, Starcrest Drive to Starview Drive:
    • Paving is complete. Manholes have been adjusted. Steel plates will be removed on May 20th. Striping is scheduled for May 20th.
  • Warm Springs Avenue, Glacier Drive to SH-21:
    • Milling is complete. Paving is scheduled to continue through May 24th. Minor work will follow paving, including manhole adjustments, permanent striping, and shouldering. 

Construction Update: May 12, 2022 - 

  • Edna Street, Five Mile Road to Patton Street:
    • Asphalt paving is complete. Permanent striping is scheduled for the week of May 9th .
  • Warm Springs Avenue, Starcrest Drive to Starview Drive:
    • Milling was completed May 11th. Paving is scheduled for May 12th and May 13th.
  • Warm Springs Avenue, Glacier Drive to SH-21:
    • Milling began May 12th. Paving is scheduled to begin May 16th and continue through the week of May 23rd.

Construction Update: May 6, 2022 - Segments include: Edna Street, Five Mile Road to Patton Street. Asphalt paving is complete. Manhole adjustments are complete. Steel plates will be removed on May 8th . Permanent striping is scheduled for the week of May 9th . Warm Springs Avenue, Starcrest Drive to Starview Drive - Milling is scheduled for May 11th . Paving is scheduled for May 12th . Warm Springs Avenue, Glacier Drive to SH-21 - Milling is scheduled to begin May 12th . Paving is scheduled to begin May 16th and continue through the week of May 23rd .

Construction Update: April 29, 2022 - Segments include: Edna Street, Five Mile Road to Patton Street. Concrete and pipe work is complete. Asphalt paving is scheduled to be complete on April 29th, weather dependent. Remaining work includes manhole adjustments and permanent striping. Warm Springs Avenue, Starcrest Drive to Starview Drive - Milling and paving is scheduled to begin May 11th . Warm Springs Avenue, Glacier Drive to SH-21. Concrete work complete. Milling and paving is scheduled to begin in late May.

Construction Update: April 22, 2022 - Segments include: Edna Street, Five Mile Road to Patton Street Concrete and pipe work is complete. Roadway work begins March 21st. Edna Street will be closed during construction. Warm Springs Avenue, Starcrest Drive to Starview Drive - Milling and paving is scheduled to begin May 11th . Warm Springs Avenue, Glacier Drive to SH-21 - Concrete work is nearly complete. Milling and paving is scheduled to begin in late May.

Construction Update: April 8, 2022- Concrete work on Edna St started January 17th and is ongoing. Pipework on Edna St is now complete. Roadway work begins on Edna St March 21st. Edna St will be closed during construction.

Construction Update: March 11, 2022 -  Concrete work on Edna St started January 17th and is ongoing. Pipework on Edna St started on February 21st and is ongoing.

Construction Update: February 10, 2022 - Concrete work on Edna St from Five Mile Rd to Patton St started January 17th and is ongoing. Pipework is anticipated to start in late February on Edna Street. 

Construction Update: February 3, 2022 - The preconstruction meeting was held on December 15th. Segments include Edna Street, Five Mile Road to Patton Street. Concrete work started January 17th and is ongoing. 

Construction Update: January 21, 2022 - The preconstruction meeting was held on December 15th. Segments include  Edna Street, Five Mile Road to Patton Street. Concrete work is scheduled to start in late January. 

 

General Description:
This winter, the Ada County Highway District will begin work on phase one of 2021 Federal Aid Capital Maintenance Project. This is a pavement maintenance project that consists primarily of the removal and replacement of either all or a portion of the existing asphalt pavement (depending on the street segment). Work also includes reconstructing adjacent curb ramps to meet modern standards and minor storm water pipe replacements. Pedestrian ramp work and concrete work is expected to start this winter, while roadwork is expected to start early spring. Construction is anticipated to end early summer of 2022. Work will be done on the following segments of road:

  • Edna Street, Five Mile Road to Patton Avenue
  • Warm Springs Avenue, Starcrest Drive to Starview Drive
  • Warm Springs Avenue, Glacier Drive to State Highway 21

Time Frame

Start Date:
December 2021
End Date:
Early Summer 2022

Return to Projects

Related Documents

Project Manager


We Drive Quality Transportation For All Ada County ~
Anytime...Anywhere

Ada County Highway District © 2017
For Questions or problems with this Web site contact the Webmaster
Privacy Policy