Ada County Highway District

2011 Overlays (Road Resurfacing Work)

General Description:

Construction on the 2011 Overlays began in July in some locations and will continue into November.  A list of locations and approximate time frames available is listed below.

Please check this page regularly for updates to construction schedules, as they are subject to change. Please call if you have any questions, (208) 387-6100.

  • See the RITA page to view all "Road Work in the Area" happening this week.

Poor_Condition_Street2.gif

What is an overlay?

Each year the condition of roads throughout Ada County is closely assessed and a priority system is used to determine which roads have the greatest need for re-surfacing. Overlay work generally involves the milling and removal of two inches of existing (failed) asphalt. A fresh layer of asphalt is then applied to the roadway, which will also receive new lane markings. The road segments selected are based on an in-depth ranking system that accounts for wear and deterioration.

Pedestrian sidewalk ramps located along the overlay road sections will be removed and replaced if they are not in compliance with Americans with Disability Act (ADA) standards.

Impacts During Construction

Overlay work is typically a fast moving process, but includes several steps, some of which can involve, but are not limited to:

  • General construction noise
  • Ground vibration
  • Equipment safety back up alarms
  • Dust
  • Night work lighting
  • Temporary lane restrictions & delays
  • Pedestrian impacts (sidewalk ramps not compliant with Americans with Disabilities Act (ADA) standards will be removed and replaced)

Some overlay locations are scheduled for night work to occur, typically between the hours of 7 p.m. and 5 a.m. Performing night work allows construction to occur faster and under safer conditions for residents, motorists and crews and reduces the need for lane restrictions or closures.

Overlay Locations

2011 Federally Funded Overlays
The following locations are funded by $1 million in federal money.

Work on the following locations is anticipated to start on Monday, September 26 or thereafter and be complete in November.

(Information last updated 11/18/11)

  • State St., Glenwood St. to Pierce Park Ln. - night work |7 p.m. to 5 a.m - The painting of lane lines will occur week of 11/21, weather-permitting.
  • Overland Rd., Vista Ave. to Latah St. - day work | Weekdays: 9am-4pm and 7-10pm; Saturdays 7am-10pm - Lane lines have been painted. Crews are finishing up work on the manhole collars within the roadway.

 2011 Local Overlays
The following road sections are part of ACHD's Local Overlay Program and are funded through $4.6 million from ACHD's Capital Projects budget.

  • Milwaukee St., Ustick Rd. to Goddard Rd. (Boise) - Work hours: 9 a.m. to 4 p.m. - complete
  • Overland Rd., Cedarwood Dr. to Curtis Rd. (Boise)  - Work hours: 8 p.m. to 5 a.m.  - complete
  • Americana Blvd., Latah St. to Shoreline Dr. (Boise) - Work hours: 8 p.m. to 5 a.m. - complete
  • Main St., 10th St. to 13th St. (Boise) - Work hours: 8 p.m. to 5 a.m. - complete

 


Work on the following locations began in early August and wrapped up in late September:

  • Emerald St., Five Mile Rd. to Maple Grove Rd. (Boise)  - Work hours: 8 p.m. to 5 a.m. - complete
  • Veterans Memorial Parkway, Chinden Blvd. to State St. (Boise)  - Work hours: 8 p.m. to 5 a.m. - complete
  • Five Mile Rd, Overland Rd. to Estate Dr. (Boise)  - Work hours: 8 p.m. to 5 a.m. - complete
  • Beacon, Broadway to ParkCenter Blvd. (Boise) - complete
  •  


    Work on the following locations began in late August and wrapped up in late September:
    • Pleasant Valley Rd., Ten Mile Creek to Hollilynn Dr. - Work hours: 8 p.m. to 5 a.m.  - complete
    • Columbia Rd., McDermott Rd. to Linder Rd. - day work  - complete
    • Black Cat Rd., Overland Rd. to Franklin Rd. -  Work hours: 8 p.m. to 5 a.m. - complete

    2011 Kuna Stimulus Overlays
    The following locations are funded by $500,000 in federal stimulus money.

    Work on the following locations began in mid-July and wrapped up in mid-August.

    Work hours for both locations are weekdays from 8:30 a.m. to 4 p.m. & 6 p.m. to 10 p.m and weekends from 6 a.m. to 10 p.m.

    • Deer Flat Rd., Ten Mile Rd. to Linder Rd. - complete
    • Avalon St., Ten Mile Rd. to Short Line St.- complete

 

Time Frame

Start Date:
July 2011
End Date:
Fall 2011

Return to Projects

Project Manager


We Drive Quality Transportation For All Ada County ~
Anytime...Anywhere

Ada County Highway District © 2017
For Questions or problems with this Web site contact the Webmaster