Ada County Highway District

Roosevelt Street, Rose Hill to Emerald Street

 

Construction Update: May 20, 2022: Hauling base for sidewalk and road. Placing pedestrian ramps and finalizing west side. Once west side is complete east side of Roosevelt will be milled.

Construction Update: May 12, 2022: Working between Rose Hill and Alpine. Excavation complete prepping for curb and sidewalk. Cleaning road for opening purposes. Curb, gutter, and ped ramps. Concrete sidewalks and approaches being installed.

Construction Update: May 6, 2022: Irrigation work is ongoing. Working between Rose Hill and Alpine. Excavation complete prepping for curb and sidewalk. Cleaning road for opening purposes. Curb, Gutter, and ped ramps. Concrete sidewalks and approaches being installed.

Construction Update: April 15, 2022: Irrigation work is ongoing. Closure between Alpine and Bethel ongoing.  Installing Sewer utilities anticipated finished April 18th. Working between Rose Hill and Alpine. Curb, Gutter, and ped ramps. Concrete sidewalks and approaches being installed. Suez will be installing water line starting March 14th  Multiple road closures as work progresses.

Construction Update: April 8, 2022: Irrigation work ongoing. Closure between Alpine and Bethel ongoing. Installing sewer utilities. Working between Rose Hill and Alpine. Curb, Gutter, and ped ramps. Seepage bed being installed. Concrete sidewalks and approaches being installed. Suez will be installing water line starting March 14th. Multiple road closures as work progresses.

Construction Update: March 11, 2022: Irrigation work ongoing. Closure between Alpine and Bethel anticipated March 14th. Installing Sewer utilities. Working between Rose Hill and Alpine. Curb, Gutter, and ped ramps. Suez will be installing water line starting March 14th. Multiple road closures as they progress.

Construction Update: March 4, 2022: Irrigation work ongoing. Closure between Alpine and Bethel postponed - Waiting for equipment before closure can happen. Installing Sewer utilities. Working between Rose Hill and Alpine -Curb, Gutter, and pedestrian ramps. Suez will be installing water line starting March 7th. Multiple Road closures as they progress.

Construction Update: February 25, 2022: Irrigation work ongoing. Closure between Alpine and Bethel postponed. Waiting for equipment before closure can happen. Installing Sewer utilities. Working between Rose Hill and Alpine - Curb, Gutter, and ped ramps.

Construction Update: February 18, 2022: Preconstruction meeting held December 16th. Irrigation work ongoing. Closure between Alpine and Bethel anticipated Feb 21st.

Construction Update: February 3, 2022: Preconstruction meeting held December 16th. NTP scheduled for January 10th. Tree trimming and removal anticipated January 18th. Irrigation work anticipated starting January 24th. Road closed for irrigation between Bethel and Morris Hill Rd.

 

General Description

The original Roosevelt Street, Rose Hill to Emerald Street project started design in 2015 and since then ACHD has modified the design to incorporate improved bicycle and pedestrian facilities. Please see below for an updated description of the project as well as updated exhibits. 

Roosevelt, Rose Hill to Alpine

  • Construct new curb, gutter and sidewalk on both sides of the street where necessary.
  • Add bike lanes to both sides of the street.
  • Construct a raised intersection at Roosevelt and Alpine to slow drivers. The intersection will also include a Rectangular Rapid Flashing Beacon (RRFB) to alert drivers to pedestrians using the crosswalk on Roosevelt.

Roosevelt, Alpine to Emerald

  • Construct a multi-use pathway for bicyclists and pedestrians on the east side of the street. The section along the Morris Hill Cemetery will include an extruded curb.
  • Add curb, gutter and sidewalk on the west side of the street.
  • Paint a bike box and bike crossing on Roosevelt at Fairmont Street to provide a path for bicyclists to enter/exit the multi-use pathway.

Existing on-street parking will be maintained on the west side of Roosevelt.

Updated Design Exhibits

Project Purpose

  • Increase pedestrian and bicyclist connectivity.
  • Increase safety for children walking and biking to local schools.

 

Design:
2015-2016 (updated 2021)
Construction:
Late January 2022

 