Cherry Lane Street Lighting Pilot Project

Project Update as of 11/30/17:  The Notice to Proceed was August 27, 2017. The first 80 working days shall be for procurement of materials. Once materials are delivered, the contractor shall have 55 cumulative working days to complete construction.

Project Description

  • This federally-funded project will help provide for continuous street lighting on Cherry Lane between Meridian Road and Linder Road. This project is in cooperation with the City of Meridian.  

Project Purpose: 

  • Increase pedestrian safety

 

Design:
FY2015
Right-of-Way:
N/A
Construction:
FY2017

Time Frame

Start Date:
FY2017
End Date:
TBD