General Description:

Work to re-paint the Capitol Boulevard Bridge began May 23, 2013 and was completed in late October 2013. 

In conjunction with Boise City, ACHD will re-paint the Capitol Boulevard bridge, and lights, similar to those originally constructed on the bridge some four-decades ago, will be added. Work began on May 23 and will be complete in the fall of 2013.

The bridge will be re-painted to its original 1930's color, Ivory Lace (an off-white shade). The bridge was last painted in 1992 during a previous bridge rehabilitation.

As part of Boise City's 150th celebration, the bridge will be re-dedicated upon completion. In conjunction with the re-painting, Boise City will replace the light fixtures on the bridge to reflect the original 1930's fixtures.

Crews will paint the bridge in two stages:

  • May to June: Crews will work on the upper portion of the bridge - Complete
  • September to October: Crews will work on the lower portion of the bridge once water levels recede for the year - Complete

Construction Impacts

Crews will work weekdays, generally between the hours of 7 a.m. and 7 p.m. When crews are working, lane restrictions on the bridge are possible. In addition, temporary Greenbelt closures or restrictions may be necessary. 

 

Time Frame

Start Date:
May 2013
End Date:
Fall 2013

Return to Projects

Project Manager

Pierson DeWit
projects@achdidaho.org


We Drive Quality Transportation For All Ada County ~
Anytime...Anywhere

Ada County Highway District © 2017
For Questions or problems with this Web site contact the Webmaster