Construction Update as of 4/12/19: This project is considered substantially complete. There are minor items left that the contractor will address.
Both the Osage Street and 46th Street box culverts are installed and ready to accept water. Valley gutter has been poured. Crews are preparing for the placement of topping slab on Osage. Paving is ongoing and should be complete by the end of this week.
The contractor for this project is Knife River Mountain West.
General Description:
The Ada County Highway District will replace Bridge #1452 over the Thurman Mill Canal on 46th Street as part of ACHD's Bridge Maintenance Program. The project will be designed and constructed concurrently with the Osage Street Bridge #1451 Project.