2018 Bridge Preventative Maintenance Project

Construction update as of 6/21/18:  The Notice to Proceed was June 11th. The project will take about two weeks to do the three bridges. Work includes the application of an epoxy overlay to the bridges.

General Description:
The Ada County Highway District will begin preventative maintenance on three bridges starting in early June:

  • S. Gekeler Lane just north of W. McGregor Drive:  Complete.
  • 9th Street between River Street and W. Royal Boulevard:  Crews are working on it this week.
  • Bogus Basin Road 3 miles north of Hill Road:  Complete.

Work will consist of applying an epoxy overlay to each of the bridges. Gekeler Lane will be completely closed during this work, and detour routes will be posted in advance of construction. Work on the 9th Street and Bogus Basin Road bridges will be done half at a time, and require only partial closures during construction.

Time Frame

 

Start Date:  June 11, 2018

End Date:  August 17, 2018

Return to Projects

Related Documents

Project Manager

Justin Bledsoe
projects@achdidaho.org


We Drive Quality Transportation For All Ada County ~
Anytime...Anywhere

Ada County Highway District © 2017
For Questions or problems with this Web site contact the Webmaster