Meridian Road & Main Street Split Corridor, Phase 1

General Description

Click here to view construction phasing plans.

May 2009 road work slideshow: Click here to view.

Watch the transition to one way:  Click here to see the video clip.

   MSCpathMay2009Web.JPG 

The Meridian Split Corridor project has been identified in the Downtown Meridian Transportation Management Plan as the number one priority of the City of Meridian.

Project Purpose

  • Improve capacity and accommodate existing and future traffic volumes along the Main Street and Meridian Road Corridor.
  • Improve the safety of the Main/Waltman/Meridian/Central intersection through realignment of the roadway.
  • Add a multi-use pathway to the east side of Main Street.

Meridian.jpg

Project Description

  • Construct the southern portion of the Meridian Road and Main Street Split Corridor, between I-84 and Franklin Road.
  • Reconstruct and realign the Main/Waltman/Meridian/Central intersection.
  • Widen Franklin Road between Meridian and Main to accommodate a longer left turn lane for traffic turning onto Meridian. 
  • Re-stripe Meridian Road and Main Street for one-way traffic.
  • Add sidewalks on west side of Main Street where they currently do not exist.

Project Area

   meridiansplitcorridorw.jpg 

Do you have questions about a business located in the area and how ACHD can help you during construction?  Click here to learn more about ACHD's Business Resources.

Time Frame

Start Date: February 9, 2009
End Date: August 2009