2017 Overlays--Arterial and Collector Capital Maintenance

General Description

2017 Arterial and Collector Capital Maintenance

This project will resurface select roads in Ada County, improving the condition and longevity of the roadway. Multiple pedestrian ramps will also be replaced and/or upgraded to comply with the Americans with Disabilities Act (ADA) standards. This will include the removal and replacement of concrete and impacts to sidewalks.

The following roadway segments have been identified for this project:

  • Park Boulevard between Broadway Avenue and Walnut Street
  • Franklin Street between Maple Avenue and Coston Way
  • McKinley Street between Avenue D and Maple Avenue
  • Haines Street from Franklin Street to the north end (north of Shenandoah)
  • Ballantyne Lane between Floating Feather Drive and Beacon Light Road
  • Ranch Drive between Eagle Road and Eagle Hills Way
  • Columbia Road between Locust Grove Road and Eagle Road
Work on Park Boulevard is permitted from 7 p.m. to 5 a.m. Monday-Friday, and anytime during the weekends. Work on all other segments will occur between 9 a.m. and 8 p.m. Monday-Friday.

Time Frame

Start Date: May 2017
End Date: August 2017