2016 Arterial and Collector Capital Maintenance

General Description

2016 Arterial and Collector Capital Maintenance

This project is substantially complete as of 11/09/16.

The following sections of roadway will have a small portion of the roadway milled off, then receive a new layer of asphalt:

PHASE I  Project update as of 8/11/16:

  • Cole Road, Lake Hazel Road to Desert Avenue
    • Complete. 
  • Five Mile Road, Fox Brush Avenue to Lake Hazel Road
    • Complete. 
  • Five Mile Road, Columbia Road to Lake Hazel  Road
    • Paving is complete. Striping is scheduled to be done within the week.  
  • Trestlewood Avenue, Five Mile Road to Misty Glen Avenue
    • Complete. 
  • Valley Heights Drive, Hidden Valley Rim to Lake Hazel Road
    • Complete. 

PHASE II  Project update as of 11/03/16: 

  • Amity Road, Five Mile Road to Maple Grove Road
    • Complete. 
  • Irene Street, Harrison Boulevard to 13th Street
    • Complete.
  • Stratford Drive, Franklin Road to Central Drive
    • Complete. 
  • Essex Way/Hollandale Drive
    • Complete.
  • Fulton Street, 9th Street to East End
    • Soft spot repair is scheduled for the weekend of November 5-6. 

 

Time Frame

Start Date: mid-June 2016
End Date: TBD