2016 Residential Capital Maintenance

General Description

This project is substantially complete as of 6/29/16. 

2016 Residential Capital Maintenance

Four subdivisions have been identified to receive pavement maintenance treatment.

  • Country Squire
  • Lamplighter Estates
  • Stardust
  • Cole Square

Treatment consists of either removing the entire existing pavement and repaving, or milling the top two inches of the pavement, followed by repaving. Repairs to sidewalks, curbs, and pedestrian ramps will be completed at select locations.

Time Frame

Start Date: April/May 2016
End Date: June 2016