Targee Street, Owyhee Street to Shoshone Street

General Description

Targee Street, Owyhee Street to Shoshone Street
Full rebuild of Targee Street between Owyhee Street and Shoshone Street

  • There will be on-street parking on the south side of Targee Street. On-street parking on the north side of Targee Street will be prohibited.
  • Sidewalk, curb, and gutter will be added on both sides of Targee Street to connect to the existing sidewalk.
  • Curb, gutter and sidewalk will also be added to a portion of Shoshone Street between Targee and Cherry.
Project Purpose:

  • Replace deteriorating pavement
  • Create pedestrian connectivity
Design:  FY2016

Right-of-Way:  FY2016-2017

Construction:  FY2018

Time Frame

Start Date: FY2018
End Date: FY2018