Linder Avenue /Main Street/3rd Street Roundabout

General Description

This project is substantially complete as of 6/24/16.

ACHD celebrated the completion of the Linder/Main/3rd project on Friday, July 8th.

Ribbon-Cutting-400.gif

Downtown-Roundabout-Kuna-300.gif

.....

Learn about roundabouts

Click here to learn more about roundabout safety, benefits and how to use them.

.....

Construction to start in February

As early as February 15, 2016 construction will begin on the Linder, Main, 3rd Street Roundabout and Pedestrian Improvement Project.

What can neighbors expect?

  • Work will typically occur between 7 a.m. and 7 p.m., and is anticipated to be complete in July 2016.
  • The Linder, Main, 3rd intersection will be closed for three months during the construction and weekend work is anticipated during the closure. In the event additional closures are requested by the contractor or a utility company, ACHD will determine the validity of the request, the length of time the road will be closed, and when it will be allowed.
  • The work will also include, but not be limited to, general construction noise, dust, equipment back up alarms, ground vibration and lane restrictions with flaggers.
  • Please note that business, emergency and adjacent residential access will be maintained at all times, even during the intersection closure.

Have questions?

We are more than happy to answer any questions you might have about the construction project. Please e-mail us at projects@achdidaho.org or call:

  • Ryan Cutler, ACHD Project Manager, 387-6202
  • Justin Bledsoe, ACHD Construction Supervisor, 387-6283

Learn more about roundabouts

Click here to learn more about roundabout safety, benefits and how to use them.

......

May 29, 2014 Open House

Please click on the links below to review the information from the open house.

...................................

Project Description

  • Construct a single-lane roundabout at the Linder Avenue, Main Street and 3rd Street intersection.
  • Include sidewalks and bicycle facilities at intersection.
  • Construct sidewalks on the south side of 2nd Street between Linder Avenue and Avenue C, and on the north between Linder Avenue and just west of Avenue A.
  • Add an enhanced pedestrian crossing at 2nd Street and Linder Avenue, and a crosswalk at 4th Street and Linder Avenue.
  • Main Street will include sharrows at the roundabout. Sharrows are pavement markings that designate a shared travel lane for bicyclists and motorists.

Where did this project come from?

This project was the top priority for the Kuna City Council from the Kuna Downtown Corridor Plan. For more information about the Corridor Plan, click here.


Time Frame

Start Date: February 15, 2016
End Date: July 2016