Construction on the 2010 Overlays began in May. Please check
this page regularly for updates to construction time frames, as they are
subject to change. Around 170 locations are impacted by ACHD
overlays this season, but not all of them are listed on this page. Most
locations can be found on our
construction map. Please call if you have any questions, (208)
387-6100
Click here to view all
"Road Work in the Area" happening this week.
A note about overlay work and
impacts:
Overlay work is typically a quick process, but includes several
steps, some of which can involve, but are not limited to:
- General construction noise
- Ground vibration
- Equipment safety back up alarms
- Dust
- Night work lighting
- Temporary lane restrictions & delays
Many overlay locations are scheduled for night work to occur,
typically between the hours of 7 p.m. and 5 a.m.
Performing night work allows construction to occur faster and
under safer conditions for residents, motorists and crews and
reduces the need for lane restrictions or closures.
To learn more about the overlay process,
click here.
Twenty five road sections in Ada County will receive a thin lift overlay. These
overlays are funded by $4.32 million in federal stimulus money. The existing
surfaces will be milled (ground) in areas with curb and gutter and at the
beginning and end of the road sections. Hot asphalt mix will then be laid down.
Road sections chosen for thin lift overlays generally have less deterioration
than those selected for a full depth overlay; however other factors like the
number of outdated pedestrian ramps in the area as well as traffic counts are
considered.
Locations: Please note that construction
time frames are approximate and are subject to change.
Unless otherwise noted, work at these
locations is allowed weekdays from 8:30 a.m.- 4 p.m. and 6 p.m. to 10 p.m.
and 6 a.m. to 10 p.m. on weekends.
Scheduled to begin in late August:
- 5th Street from Main Street to Jefferson Street - Night Work Allowed
(9p.m.- 5 a.m.)- Initial work to begin Sunday,
8/ 29. Milling, Monday, 8/30 and Tuesday, 8/31. Paving, Thursday, 9/ 2. Work
should be mostly complete after Wednesday 9/8.
- Ballantyne Lane from West State Street to Floating Feather Road -
Initial work to begin Tuesday, 8/31. Milling,
Wednesday, 9/1. Paving, Tuesday 9/7 and Wednesday, 9/8. Work should be
mostly complete by Friday, 9/10.
- Gowen Road from Broadway Street to Interstate 84 -
Work to begin in late September or early October
- Park Lane from Floating Feather Road to Beacon Light Road -
Work to begin in early September
- Park Lane from State Highway 44 to Floating Feather Road -
Initial work to begin Thursday, 9/2. Milling, Friday,
9/3.
- Pine Avenue from 2150 Pine Avenue to Linder Road -
Work to begin in mid-September
- Ten Mile Road from N. of McMillan Road to Chinden Boulevard -
Work to begin early to mid-September
- Ten Mile Road from north of Ustick Road to McMillan Road -
Work to begin early to mid-September
- Ustick Road from McDermott Road to Black Cat Road -
Work to begin early to mid-September
Complete: Roads have been paved, however some locations may still require manhole work and lane
striping.
- 13th Street from Jefferson Street to State Street
- Apple Street from Boise Avenue to Parkcenter Boulevard
- Boise Avenue from Gekeler Lane to Apple Street
- Cloverdale Road from Camas Street to Franklin Road
- Cloverdale Road from Ustick Road to Meadowwood Drive
- Floating Feather Road from Edgewood Drive to State Highway 55
- Lake Forest Drive from Quamash Way to Flax Place -
Completion pending.
- Lake Hazel Road from Cloverdale Road to West of Five Mile Road
- Latah Street from Alpine Street to Americana Boulevard
- Ustick Road from Locust Grove Road to just west of Leslie Way
- Victory Road from Five Mile Road to Maple Grove Road
- Cole Road from Franklin Road to Fairview Avenue
- State Street from Pierce Park Road to Collister Drive
- Orchard Street from Interstate 84 Ramp to Overland Road
- Franklin Road from McDermott Road to Black Cat Road
- Ustick Road from Black Cat Road to Ten Mile Road
To view a map of the thin lift overlay locations,
click here.
The 2010 federal overlay projects are being funded by $6.55 million in
federal stimulus money. The following list of 17 locations will receive
“full depth” overlays, meaning some locations will first undergo the removal
of the existing road surface, followed by new asphalt. Pedestrian ramps
adjacent to the overlay locations will be upgraded or replaced and brought
to current Americans with Disabilities Act (ADA) standards where needed.
Locations: Please note that night
work hours are typically 7 p.m. to 5 a.m.
Some work may occur simultaneously at more than one location.
Time frames are subject to change, as overlay work is weather-dependant.
Work at the following locations will occur in August
through the end of September. Most of the work is scheduled to occur at night,
generally during the hours of 7 p.m. to 5 a.m.
- Curtis Rd., Cassia St. to Franklin Blvd. -
on hold until
further notice
- Fairview Ave., Orchard St. to Bluff St. - work
to begin approx. 8/23
- Main St., 13th St. to 16th St. - work to begin
approx. 8/18
- Capitol Blvd., University Dr. to Front St. -
work to begin approx. 8/16 or thereafter
- Emerald St., Curtis Rd. to Orchard St. - work
to begin approx. 8/23
- Overland Rd., Curtis Rd. to Orchard St. - work
to begin approx. week of 8/9
- Overland Rd., Maple Grove Rd. to Entertainment Ave. -
paving complete
- Overland Rd., Orchard St. to Latah St.-
paving complete
- State St., 23rd St. to 16th St. - work to begin
approx. 8/19
- Vista Ave., Rose Hill Rd. to Overland Rd.- work
to begin approx. 8/10 or thereafter
Complete: Roads have been paved, however some locations may still require manhole work and lane
striping.
- Meridian Rd., Ustick Rd. to McMillan Rd. -
Night Work Allowed
- Ustick Rd., Meridian Rd. to Locust Grove Rd. -
Night Work Allowed
- McMillan Rd., Locust Grove Rd. to Eagle Rd. -
Night Work Allowed
- Cloverdale Rd., Savage Dr. to McMillan Rd. - Night Work Allowed
- Franklin Rd., Five Mile Rd. to Maple Grove Rd. -
Night Work Allowed
- Overland Rd., Five Mile Rd. to Maple Grove Rd. -
Night Work Allowed
- Fairview Ave, east of Milwaukee St. to Cole Rd. -
Night Work Allowed
To view a map of the Federal Full Depth Overlay locations,
click here.
Local overlays are funded with money from ACHD’s Capital Projects budget.
This year $1.6 million was approved by the ACHD Commissioners. These
locations will receive
full depth overlays.
Locations:
Note: Construction is anticipated to begin in September 2010.
Specific time frames have not been determined.
- ParkCenter Boulevard from Beacon Street to Bown Way
- ParkCenter, Apple to Bown:
work allowed from 9 a.m.-4 p.m. (weekend work is possible)
- Work will begin September 7, or
thereafter on this stretch of ParkCenter.
- ParkCenter, Beacon to Apple: work allowed from 8
p.m.-5 a.m.
(weekend work is possible)
- Deer Flat Road from State Highway 69 to Linder Road
- Work allowed from 7 a.m.- 9 p.m., weekends only
- Currently
anticipated to begin September 25.
- Intersection of Fairview Avenue and Mitchell Street
- Work allowed from 8 p.m.-5 a.m. (weekend work is
possible)
- Currently anticipated to begin October 4.
- Intersection of Fairview and Locust Grove
- Work allowed from 8 p.m.-5 a.m. (weekend work is
possible)
- Currently anticipated to begin September
28.